Surrey council overspends £1.6m on fire safety doors

A council in Surrey has overspent by £1.6m on a major fire safety project after failing to work out how many fire doors actually needed replacing.

Assumptions from incomplete data left officers underestimating how many fire doors needed replacing in Guildford Borough Council’s housing stock.

Outside Guildford Borough Council's HQ, Millmead House. (Credit: Guildford Borough Council)placeholder image
Outside Guildford Borough Council's HQ, Millmead House. (Credit: Guildford Borough Council)

A new report reveals the council has already spent £4.1m on the fire door replacement scheme – far above the original £2.5m contract estimate.

Now a further £1.6m is needed to complete the project, bringing the total to £6.5m.

The overspend seems to have stemmed from a failure to properly assess the scale of the work needed before signing the contract in 2022, according to the report.

Officers relied on incomplete data and so were not fully aware of the sheer number of doors which were non-compliant.

Councillors tried to remain positive amidst the dramatic overspend.

Cllr Catherine Houston referenced the importance of being a dutiful landlord to residents.

She said: “Regardless of [the overspend] I think it is wonderful that, in the light of Grenfell, we are taking real care, making sure our residents are safe, particularly against fire.”

Leader of the council, Cllr Julia McShane labelled the unexpected cost as a “slight overspend” but reassured the executive how important fire safety is.

She added the new contact also acquired the doors at the same price as in 2022 making a “saving”.

Cllr Tom Hunt described it as a “learning experience”, while Pedro Wrobel, joint chief executive of the council, said: “Whilst it is frustrating we did not catch this before breaching the budget, at the very least we caught it very shortly afterwards.

“We are once again looking at our controls, not just in housing but across the piece, to make sure we have as firm a grip as possible on this.”

The form of contract allowed work to be ordered when needed rather than fixed in advance, meaning the true cost ballooned as the council discovered more non-compliant doors.

Additional blocks and fire safety improvements were added mid-way through the project.

Despite the overspend, no extra funding is being asked for at this stage.

Instead, officers sought retrospective approval from the executive for the budget overrun and say the costs will be covered from elsewhere in the capital programme.

Officers emphasised the overspend is from the council’s estimated budget costs, rather than with the contractor itself.

Officers told the executive the overspend happened for a variety of reasons and council bosses are now reviewing the mistakes and will put in place measures to stop it happening again.

Guildford council ’s fire safety efforts follow a self-referral to the Regulator of social housing in 2023.

After the authority admitted it was not fully compliant with building safety standards, the regulator issued a C3 rating, flagging serious weaknesses in the council’s oversight of its housing stock.

Related topics:
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice