Harlequin Theatre works could begin in November – but costs may cause delay
Construction work to refurbish the Harlequin Theatre in Redhill could begin in November.
Reigate MP Rebecca Paul shared an update she had received from the local authority about the plans.
A planning application was submitted on September 9 for the refurbishment and upgrading of the theatre. The proposals include replacing the roof covering, improving mechanical and electrical systems, associated building work and enhanced health and safety measures.
The application is expected to be determined in November, while the council has instructed that scaffolding be designed ahead of the proposed work.


The technical design phase is expected to be completed by the end of October, when Reigate and Banstead Borough Council also hopes to receive a detailed price from the contractor.
Mrs Paul said: “Please note that if the price is more than expected that could generate a delay.”
Subject to planning permission, an acceptable contractor’s price and permission being secured from the leaseholder, construction is expected to begin in November.
The council is also continuing contract negotiations with its preferred theatre operator.
Mrs Paul said community access had formed part of those discussions and that all requests, made by the Harlequin Support Group, had been shared with the preferred operator and were informing negotiations.
The agreement with the theatre operator is tied to the construction contract.
According to the MP, the council still plans for the successful operator to run both the Harlequin Theatre and Unit 5 at The Rise in central Redhill. The two venues would form a combined flexible arts, leisure and cultural offer.
She said: “Residents previously have asked me why the council hasn’t considered different operators for each site, given that Unit 5 can be up and running much quicker than the theatre, but I’m still waiting for an answer on that.
“I’ll update when I hear.”