Christmas rail disruption warning for Surrey and Sussex as busy station faces two weeks of engineering work

Rail passengers travelling between Surrey and Sussex face major disruption, over Christmas and the New Year.

Trains through Redhill station – near Gatwick Airport and Crawley – are set to be replaced by buses for two weeks.

More than a mile of track will be renewed around Redhill station as part of a £31.7 million programme of railway improvements, with the work due to begin on Sunday, December 20, and continue until Sunday, January 3.

The closure will affect passengers travelling between London, Surrey and the Sussex coast, as well as those heading to Gatwick Airport during one of the busiest holiday periods of the year.

Rail passengers travelling between Surrey and Sussex face major disruption, over Christmas and the New Year. Photo: Network Railplaceholder image
Rail passengers travelling between Surrey and Sussex face major disruption, over Christmas and the New Year. Photo: Network Rail

Although trains will continue to run through the area on the fast lines, all services passing through Redhill station itself will be replaced by rail replacement buses.

Six stations will have no train services during the works: Earlswood, Redhill, Merstham, Coulsdon South, Nutfield and Godstone.

The disruption will affect several routes, with Southern, Thameslink and Great Western Railway services all facing changes.

Southern trains between London Victoria and Reigate will not run, while services between Redhill and Tonbridge will operate only between Edenbridge and Tonbridge.

Passengers travelling between Reading, Guildford and Gatwick Airport will also be affected, with Great Western Railway services terminating at Reigate instead of continuing to Redhill and the airport. Replacement buses will run between Reigate and Gatwick Airport.

Thameslink services between Purley and Horley via Redhill will also be suspended.

The changes could cause particular difficulties for people travelling to and from Gatwick Airport, as well as those visiting family, friends or heading away for the Christmas break.

Some Southern trains between London Victoria and the Sussex coast will make additional stops at Purley and Horley to help accommodate passengers.

Rail replacement buses will operate on a number of routes, including between Purley and Horley, calling at Coulsdon South, Merstham, Redhill, Earlswood and Salfords.

Passengers will also be able to use Metrobus routes 100, 400, 420 and 460 between Redhill and Three Bridges at no extra cost, with tickets accepted on these services.

The engineering programme will see new track switches and crossings installed, allowing trains to move between different tracks, alongside the replacement of two sections of railway with new rails, sleepers and ballast.

Network Rail says completing the work in one extended closure over the festive period will avoid the need for numerous disruptive weekend closures in the future.

Further maintenance will also be carried out between Merstham and Redhill, including replacing worn track timbers, testing rails for internal defects and inspecting signalling equipment, level crossings and other railway infrastructure.

Lucy McAuliffe, Network Rail's Sussex route director, said the extended closure was necessary to carry out the work, adding that the Christmas period had been chosen because passenger numbers were typically lower than at other times of the year.

She said: "We recognise this period includes Christmas shopping and people travelling to visit family and friends, which is why we're asking everyone, and not just regular commuters travelling through Redhill, to plan their journey and check before they travel."

Jenny Saunders is the customer services director for Southern and Thameslink.

She said: “I’d like to apologise for the changes to our services passing through Redhill station this festive season.

“While there will still be trains running through the area on the fast lines, those on routes that go via Redhill will either not run at all or be replaced by buses.

“Southern services from Tonbridge will operate no further than Edenbridge with buses covering the last stretch to and from Redhill.

“Please do go online to one of our websites to plan your journey and see how it might be affected. You may need to take a rail replacement bus which will regrettably take longer.”

There will also be significant changes for motorists using Redhill station.

Car park 2 will close from December 20 until January 4, 2027, while the car park at the front of the station will shut from 10pm on Thursday, December 17, until the end of Sunday, January 3.

The closures are needed to provide space for the engineering work and allow rail replacement buses to operate safely.

The subway between Marketfield Way and Redstone Hill, which passes underneath the railway, will also close from shortly after midnight on December 20 until 12.59am on Tuesday, December 29.

Passengers are being urged to check their journeys before setting off, particularly if travelling to Gatwick Airport or connecting with services towards the Sussex coast.